Commissioning and service
A plant is handed over when it runs at production rate with the client's own operators. The engineers who design and build a system also test it, start it up, train the people who will run it and support the plant after handover.
Commissioning
Six steps, from our workshop to production rate. Each one is completed and signed off before the next begins, and each leaves a record the client keeps.
- 01
Factory acceptance test
Panels and software tested in our workshop against the I/O list and the control philosophy. The client is invited to witness.
FAT report and punch list - 02
Installation check
Cable routing, terminations, earthing and instrument mounting checked on site against the drawings.
Inspection checklist - 03
Loop checks
Every signal tested from the field device to the screen, and every motor run in its correct direction.
Signed loop sheets - 04
Trials without product
Sequences, interlocks and alarms proven with water or empty, before any material enters the plant.
Trial log - 05
Site acceptance test
The system tested with the client against the agreed protocol.
Signed SAT protocol - 06
Start-up
The plant started section by section and brought up to production rate, with our engineers on shift until it runs steadily.
Start-up report

Training and handover
Operators are trained on the screens they will use, and the plant's electrical and instrument staff on the panels, field devices and programs. The handover documents let another engineer follow the system.
- Operator training on the HMI and SCADA
- Maintenance training for electrical and instrument staff
- As-built drawings, manuals and program backups
- Recommended spare parts list
After handover
Support comes from the engineers who know the system, because they built it.
Breakdown support
A call to our service line reaches an engineer who can talk the plant team through the fault, and travel to site when needed.
Annual maintenance contracts
Scheduled visits to inspect, clean and test panels and instruments, with breakdown support at any hour.
Changes and upgrades
New products, recipes and equipment added to the program as production changes, and older systems extended.

An annual maintenance contract covers
- Scheduled preventive maintenance visits
- Breakdown support, 24 hours a day, 7 days a week
- Program changes and up-to-date backups
- Spare parts for the systems we supply
Start-ups abroad
Our engineers travel with the system and stay until it runs. Recent projects outside India:
| Year | Project | Client | Location | Scope |
|---|---|---|---|---|
| 2023 – 2025 | Powder plant electrical, instrumentation and automationDetergents and soaps | RSPL | Bangladesh | Turnkey E&IAutomation |
| 2023 – 2025 | Bar plant electrical, instrumentation and automationDetergents and soaps | RSPL | Bangladesh | Turnkey E&IAutomation |
| 2022 – 2023 | Electrical distribution (MCC) and perfume dosingDetergents and soaps | RSPL | Ethiopia | PanelsDosing |
| 2022 – 2023 | Perfume dosingDetergents and soaps | Hindustan Unilever | Hetauda, Nepal | Dosing |
| 2019 – 2020 | Plant consultancy, utility automation and LABSA back-pressure controlDetergents and soaps | RMC | Philippines | ConsultancyAutomation |